Pinellas County Utilities (PCU) is completing a water main improvement project in St. Pete Beach, along Pass A Grille Way and Gulf Way from 9th Avenue to 22nd Avenue, where we will replace most of the aging distribution system pipe. This project will include the relocation of pipe to the main streets, the replacement of all cast iron and galvanized pipes and the addition of new service lines, meter boxes and fire hydrants.

Tentative Schedule


MilestoneSchedule
Construction notice to proceedJanuary 18, 2024
Official contract start of constructionFebruary 1, 2024
Contractor's target construction mobilizationMarch 1, 2024
Contractor's target end of constructionFebruary 1, 2025


Project Goals

  • Replace old and deteriorating cast iron pipe and galvanized pipes
  • Minimize dead-end water mains and improve water quality
  • Improve water circulation to minimize water aging
  • Improve public safety with the addition of new fire hydrants

Funding Source

This project is funded by Pinellas County Utilities Water Enterprise funds.

Contact

Guillermo “Billy” Bay, E.I.
Project Manager
Utilities
14 S. Fort Harrison Ave., Clearwater, FL 33756
(727) 464-4220
bbay@pinellas.gov

Facebook Twitter Email

Other News in City News

IMG_1006

Department Updates: Parks & Recreation

Posted on: February 13, 2024
Join our team

New Hiring Alert: City Manager

Posted on: January 30, 2024
Flooding in St. Pete Beach

Expedited Permit Procedures

Posted on: September 22, 2023
tree

St. Pete Beach Beautification Program

Posted on: January 10, 2023